Read first. This material is educational, rewritten from public research (textbooks, SPE papers, standards summaries). It is not an official API or NORSOK standard, and it does not replace operator standards, company procedures, and engineering judgment. Numbers flagged as “varies by operator” or “check the original standard” must not be used as design numbers. Final completion design uses nodal-analysis software and the operator standards in force. Units are API units (psi, ppg, ft, bbl/d) unless stated otherwise, with SI conversions where helpful.

Design workflow — how a completion engineer designs a completion

Work the steps in order. Tick each checklist item as you complete it — your progress is saved on this device. Each step links to its calculator and its reference module.

Step 0 — Gather the data: reservoir, well, fluids

Every design decision downstream depends on this data. Do not start selecting equipment before the data is confirmed.

Step 1 — Choose the completion type

Decision guide — match the sandface and the number of zones to the reservoir:

If the reservoir is…ConsiderWatch out for
Hard, consolidated, stable rock; no sand; single homogeneous zoneOpen-hole (barefoot)No zonal selectivity; cannot shut off water/gas
Soft / heterogeneous rock, multiple zones, water or gas control neededCased-hole, cemented & perforated (most common)Perforation skin; only ~6–8% open area at 12 spf
Competent rock needing borehole support, not cement isolationUncemented / slotted linerLimited isolation; slot plugging/erosion
Two zones at different pressures, simultaneous productionDual / multiple-stringCost, complex wellhead, difficult workover
High intervention / logging need, high rateMonoboreLarge tubulars, cost, PBR seal design
High-cost offshore, water/gas shut-off without interventionIntelligent / smart completion (ICV + sensor + 2 intervals)Cost, complexity, more leak paths
Unconsolidated sand, horizontal wellOpen-hole gravel pack / standalone screen — see Step 5Running risk, plugging/erosion
Shale / tight rock (k < ~0.1 mD)Horizontal + multistage frac (plug-and-perf or sliding sleeve)Stage isolation failure, frac hits, screen-out

Step 2 — Choose the completion equipment

Typical single-string stack, bottom to top: re-entry guide → bottom no-go nipple → perforated pup joint → top selective nipple → seal-bore extension → production packer → tubing → sliding sleeve (SSD) → side-pocket mandrels (if gas lift) → flow couplings → SSSV → tubing hanger.

Step 3 — Check pressure ratings & barriers

The lowest-rated element governs. Check every element against the same worst-case pressure–temperature–fluid envelope, in flowing and shut-in cases.

Step 4 — Choose artificial lift (or confirm natural flow)

Decision rule: the well flows naturally only if the IPR and VLP curves intersect above the minimum stable/economic rate. If not, lift is required — and a pump will not fix a plugged perforation, a closed valve, or a constrained separator, so diagnose first.

If…Consider
Highest rates, deep, high water cutESP (gas/solids sensitive; needs cable, penetrator, Y-tool if access below pump is required)
Gas supply available, sand / high GLR, deviated / horizontalGas lift (side-pocket mandrels at designed depths; valve spacing is design-specific)
Low rate, onshore, viscous oil, simple and reliableSucker-rod pump
Viscous oil, sand-laden, low–moderate ratePCP (elastomer temperature/chemical limits)
Liquid-loaded gas well, low cost, reservoir gas energy sufficientPlunger lift
Deep, deviated, abrasive fluidsHydraulic (jet / piston) pump

Step 5 — Check gravel pack / sand control (if needed)

Sand control is needed for unconsolidated / weakly consolidated sandstone, especially at high rate / high drawdown / high water cut and in gas wells. It is not needed for competent, well-cemented sandstone or carbonate at moderate drawdown — there, rate control below the critical drawdown (“sand management”) is the economic alternative.

Step 6 — Final check, overbalance, and handover

Overbalance is deliberately small in normal operations — typically 50–300 psi (0.1–0.5 ppg) in drilling and ~200–400 psi for completion fluid. Perforating overbalance is 100–1,000 psi; clean underbalanced perforating needs 500–1,000 psi in laboratory tests (field practice increasingly relies on dynamic underbalance).

Four key ideas

  1. Two independent, tested barriers at all times (NORSOK D-010 / ISO 16530-1).
  2. There is no universal completion — match the completion to reservoir, fluid, and well type.
  3. Tubing size is a nodal-analysis trade-off: too big → liquid loading / low velocity; too small → friction loss.
  4. Pressure ratings are one system — tubing, packer, SSSV, wellhead, and tree must all clear the same worst-case pressure–temperature–fluid envelope; the lowest-rated element governs.